I know we can pause or stop a project on X Verification or Submissions.

What does "Per URL" do?

To my understanding, a project will stop/pause when this is checked, only when each of the target links receives that number of submissions/verifications.

That is true whether the targets are in the project list (Project>Data>Target URL list) or even a Project linked to as a tier, or multiple projects linked as tiers.targets derived from setting the project as a tier to another.

Is this right? Anyone who can clarify, I would appreciate the help.  Many thanks! :confused:

Comments

  • SvenSven www.GSA-Online.de
    IF you have that "per URL" checked, it multiplied the stop/pause settings with the amount of URLs you have in the project data (of taken from main project).
  • DeeeeeeeeDeeeeeeee the Americas
    OK. 
    Thank you,  Sven. :smile: