When scheduled and paused start new project

Not sure if this is possible or if it will benefit everyone.. I run 20 projects at a time and switch to new project every 30 minutes. I also have some of my projects set to pause for 1440 minutes after 30 links are built to each url. So, to the actual feature request: When the scheduler is running and a project is set paused, can the scheduler start a new project instead of waiting? Thanks

Best Answer

  • SvenSven www.GSA-Online.de
    Accepted Answer
    Yes i can. You have an option on the scheduler dialog at the bottom for that.